refer to page 11 of Qr report....

"cost overruns in a power plant project in Sabah, arising from additional scope of works beyond the initial agreement as well as significant increased manpower
deployment to mitigate project schedule delays. Management is currently in active discussions with the main contractor on the recoverability of these additional costs incurred. "
meaning that this additional can claim back from maincontractor