Mitrajaya accepts RM42.81mil fourth variation order for data centre project

TheStar Tue, Jan 20, 2026 06:38pm - 1 month View Original


KUALA LUMPUR: Mitrajaya Holdings Bhd’s wholly-owned subsidiary, Pembinaan Mitrajaya Sdn Bhd, has accepted a fourth variation order worth RM42.81mil for data centre main works in Kuala Lumpur.

In a filing with Bursa Malaysia, the group said the variation order, accepted on Dec 10, 2025, was issued by NEXTDC Sdn Bhd and covers Stage 1 Phase 3 of the data centre project.

Following the latest variation, the revised contract sum now stands at RM844.66mil.

The works under the fourth variation order are expected to be completed by July 28, 2026.

...

Full Article on TheStar

The content is a snapshot from Publisher. Refer to the original content for accurate info. Contact us for any changes.